http://www.hhqhq.com岩棉板大多用于建筑方面,属于外墙保温的一种,很多岩棉板厂家也因此扩大了加工车间,同时打价格战,让岩棉板价格有一定的优势,吸引更多的客户。那岩棉板施工前后的八方面要点注意具体是什么?
Rock wool board is mostly used in construction, which belongs to a kind of external wall insulation. Therefore, many rock wool board manufacturers have expanded their processing workshops and fought a price war to give rock wool board a certain price advantage and attract more customers. What are the eight key points before and after rock wool board construction?
1.岩棉板外墙外保温施工期间,基层及施工环境温度低于5℃时不得施工。在五级以上大风天气和雨、雪天气不得施工。施工时及施工后,应采取有效措施防止雨水冲刷及烈日暴晒,并应及时做?;げ?。如施工中突遇降雨,应采取措施防止雨水冲刷墙面;冬季施工应按照相关标准采取防冻措施。
1. During the construction of external insulation of rock wool board exterior wall, the construction shall not be carried out when the temperature of base course and construction environment is lower than 5 ℃. Construction shall not be carried out in windy weather above level 5 and rainy and snowy weather. During and after the construction, effective measures shall be taken to prevent rainwater scouring and scorching sun exposure, and a protective layer shall be made in time. In case of sudden rainfall during construction, measures shall be taken to prevent rainwater from scouring the wall; Antifreeze measures shall be taken for winter construction in accordance with relevant standards.
2.大面积施工前,按规定应在现场采用相同材料,构造做法和工艺制作样板墙,并经有关各方确认后方可进行工程施工。
2. Before large-scale construction, the same materials, construction methods and processes shall be used to make the sample wall on the site according to the regulations, and the project construction can be carried out only after being confirmed by the relevant parties.
3.用岩棉板施工时,操作工人应佩戴好劳防用品,做好职业健康?;?,并注重施工安全。
3. When using rock wool board for construction, operators should wear labor protection articles, do a good job in occupational health protection, and pay attention to construction safety.
4.岩棉板外保温系统有关必检的材料应送有资质的检测机构进行检测,检测合格方可使用。
4. Materials related to the external insulation system of rock wool board that must be inspected should be sent to a qualified testing organization for testing, and can be used only after passing the testing.
5.岩棉板的粘贴宜采用条粘法或点粘法,涂胶面积不应小于50%。岩棉板抹完胶粘剂后,应先将保温板下端与基层粘贴,岩棉板应自下而上沿水平方向横向铺设,并应采取边铺边锚固,板缝应自然靠紧,板间缝隙不得大于2mm,如缝宽2mm时,应有保温材料填充处理,相邻板面应平齐,板间高差不得大于1.5mm。
5. The sticking of rock wool board should adopt strip sticking method or point sticking method, and the gluing area should not be less than 50%. After the adhesive is applied to the rock wool board, the lower end of the thermal insulation board should be pasted with the base course first. The rock wool board should be laid horizontally from bottom to top, and should be anchored while laying. The board joints should be naturally close, and the gap between the boards should not be greater than 2mm. If the joint width is 2mm, there should be thermal insulation material filling treatment, the adjacent board surfaces should be flush, and the height difference between the boards should not be greater than 1.5mm.
6.所有可达岩棉板的穿墙管线与构件,其出口部位应用相同材料填实后进行防水密封处理。
6. The outlet of all through wall pipelines and components that can reach the rock wool board shall be filled with the same material and then treated with waterproof sealing.
7.如在施工过程中发现贴面层脱落,应及时采取粘结或者用锚固件锚固的方式固定,并及时进行外饰面层施工。
7. If the veneer layer is found to fall off during the construction process, it should be fixed in a timely manner by bonding or anchoring with anchors, and the exterior decoration surface layer construction should be carried out in a timely manner.
8. The construction of Jinan rock wool board plastering layer shall meet the following requirements:
岩棉板粘贴完毕,应对板的抹灰面进行表面处理,用不锈钢抹刀对整个表面涂刮抹面胶浆(厚度1~1.5mm),并压入岩棉板的表层纤维中。抹面胶浆应严格按照产品使用说明书进行配置,配置好的胶粘剂应避免太阳直射,并应在2h内用完。
After the rock wool board is pasted, the plastered surface of the Board shall be treated, and the whole surface shall be coated with plastering paste (thickness 1 ~ 1.5mm) with a stainless steel spatula, and pressed into the surface fiber of the rock wool board. The plastering glue should be configured in strict accordance with the product instructions. The configured adhesive should avoid direct sunlight and should be used up within 2H.
抹面层分二层进行。较好层抹面胶浆厚度2~3mm,应先用不锈钢锯齿抹刀抹灰,后用大抹刀抹平,并趁湿压入玻纤网布,待胶浆稍干硬至可触碰时安装锚固件,用抹面胶浆封堵锚固件塑料圆盘及其周边;较好层抹面胶浆稍干可进行第二层抹面胶浆施工,厚度2mm左右,抹平并使抹面层厚度达到设计要求。
The plastering layer is divided into two layers. The thickness of the better layer of plastering glue is 2 ~ 3mm. It should be plastered with a stainless steel serrated spatula first, then leveled with a large spatula, and pressed into the glass fiber mesh while it is wet. When the glue is slightly dry and hard enough to touch, install the anchor, and block the plastic disc of the anchor and its surrounding with the plastering glue; The better layer of plaster mortar is slightly dry, and the construction of the second layer of plaster mortar can be carried out, with a thickness of about 2mm. Trowel and make the thickness of the plaster layer meet the design requirements.
此外岩棉保温板施工时需保持表面干燥、无油脂、无锈蚀等条件,为了利于防腐,可采取适当涂层,更多相关信息您可以来我们网站http://www.hhqhq.com看看。
In addition, during the construction of rock wool insulation board, the surface should be kept dry, free of grease, rust and other conditions. In order to facilitate corrosion prevention, appropriate coating can be adopted. For more relevant information, you can come to our website http://www.hhqhq.com have a look.